Jan
18
2016
By hazel.cooper
ENWL require the upgrade of the existing car park surface including surface drainage, and white lining.Green PM were appointed to manage the project, working with end users and the contractor to ensure minimum disruption occurred to staff. A key criteria of the scheme is to maintain sufficient falls across the site ensuring adequate drainage occurs to prevent further ponding.